D-B Recapitalize Deep Draft Berthing Wharf Charlie C-2

D-B Recapitalize Deep Draft Berthing Wharf Charlie C-2

D-B Recapitalize Deep Draft Berthing Wharf Charlie C-2 Highlights Placed 4,135 tons of piles, including 124 king piles (92’ long, 51,000 lbs each) and 282 sheet piles (64’ long, 6,900 lbs each) Extensive dewatering of excavations 10’ to 20’ below sea level Two...
Design-Build Emergent Repairs for 6 STI Tanks

Design-Build Emergent Repairs for 6 STI Tanks

Design-Build Emergent Repairs for 6 STI Tanks Highlights Removed and replaced six 10,000-gal STI above-ground fuel tanks Site work performed at night to minimize impact to Base operations Project completed 6 weeks ahead of schedule CMS executed a $3.4M design-build...
Flex Lab Facility

Flex Lab Facility

Flex Lab Facility Highlights Prime mechanical subcontractor for a $54M multidisciplinary research building University-wide compatible BAS HVAC modular control system “2018 Award of Excellence in Construction – Mechanical/Commercial” category, Associated Builders and...