Construction Services for Hangars J and K and TSF Paving
Location: Cape Canaveral Air Force Station, FL
Client: US Air Force
Value: $3.2M
Highlights
- Design-Build (D-B) project
- Milling/Repaving of 426,232 SF (47,359 SY) of hot mix asphalt (HMA) hangar access and parking pavement
- D-B 1,100 SF pre-engineered metal building (PEMB)
CMS completed this design-build project to mill and replace over 426,200 SF of HMA in the compound areas of Hangars J and K, the area outside to the main road, and a portion of the Technical Support Facility (TSF) parking area.
New construction included installing a 1.5” potable water supply from Hangar J to the General Maintenance Building and replacing two sanitary sewer lines from Hangar J to the sewer manholes. The crew also relocated existing conduit and installed new 2.5” PVC communication conduit, repaired sidewalks, improved site drainage, installed trailer tie-down anchors, restriped pavement, and built a 1,100 SF PEMB (the Barrel Storage Building).